Services

We develop projects and consultancy focused on urban development for the public and private sector in areas such as Public Lighting, Distributed Electric Energy Generation, Energy Efficiency and Electro mobility.

Wind Farm

Supply of equipment and provision of services on internal distribution networks, unit substations, elevating substations, transmission lines and connections with the substations from the basic power network and commissioning

Power Substations

Construction work under a fixed-price contract of power transforming substations, including detailed project execution, management of all technical documentation, electrical analysis, equipment supply, materials, civil works, electromechanical assemblies, tests, commissioning e start-up.

Hydroelectric Power Plant

Implementation projects for PCH and CGH plants, comprehending executive, mechanical and civil projects.

Transmission Lines

Services of construction, suppression, civil base, towers assembly and cables setup.

Listing of Works Already Executed by the Technical Staff

Substations and Transmission Lines 69/138/230/440kV (Chronological order)

USINA DA MATA SUBSTATION in Valparaiso: 138kV Substation. Connecting the plant to the system. Partnership with São Paulo’s Areva-T&D BSS (Service)

BORBOREMA SUBSTATION in Borborema/SP from REDE Group: bay 138 addition, control system retrofit and LT69kV relocation to São Paulo’s AREVA-T&D BSS (Service) Group. Supply of civil project and electrical, civil and electro mechanical material.

DURATEX in Agudos/SP: 138kV Substation enlargement, plus 01 37,5/40MVA-138/13,8kV to São Paulo’s Siemens Ltda. Group.
Supply of civil project and electrical, civil and electromechanical material.

VOITH EQUIPAMENTOS Industrial unity located in Jaraguá/SP: New 138kV Substation Construction with 02 15/20MVA transformers, connected to LT138kV power distribution company Eletropaulo and MT15kV cable assembly inside the factory. Directed to São Paulo’s Siemens Ltda. Group with earthwork and supply of projects and civil, electrical and electromechanical material.

LABORATÓRIOS ACHÉ in Guarulhos/SP: Supply of project, materials and electromechanical assembly of the new 138kV Substation Aché with 01 7,5/9,37MVA-138/13,8kV transformer, connected to the Bandeirantes system. Work for São Paulo’s Areva-T&D BSS (Service) group.

MONTE AZUL PAULISTA SUBSTATION CPFL Paulista: power transformer exchange, electrical voltage regulator assembly, control system retrofit and civil rebuild. Supply of civil project and electrical, civil and electromechanical material. Work for São Paulo’s Siemens Ltda group. Mutinga Avenue, Pirituba/SP

MONTE APRAZIVEL SUBSTATION CPFL Paulista: power transformer and electrical voltage regulator exchange, control system retrofit and civil rebuild. Supply of civil and electromechanical project and civil, electrical and electromechanical material. Work for São Paulo’s Siemens group.

SERVICE PACKAGE
05 138 and 69kV Substations CPFL Paulista: out bay LT enlargement and Disj3p138kV circuit at the following substations:
*Caiçara_Bebedouro SP Substation;
*Pirangi SP Substation;
* Pioneiros – S. Joaquim da Barra SP Substation;
* Humaitá-Sertãozinho SP Substation;
*Iguape Ribeirão Preto SP Substation;

Work for Areva T&D Service Group, São Paulo. Supply of civil and electromechanical project and construction.

VIVO CPD SUBSTATION in Barueri SP
02 25/33MVA units. Supply of civil and electromechanical project, construction work, grounding network e electromechanical assembly for São Paulo’s Siemens Ltda

SULZER PUMPS SUBSTATION in Jundiai SP: New 138kV substation, 50MVA and 7,5MVA transformer supplying energy for the factory and for testing Petrobras’ pré-sal pumps engine. Contract in partnership with Siemens Ltda. Supply of civil and electromechanical project, construction work, grounding network e electromechanical assembly.

AMBEV SUBSTATION in Agudos SP: New 138kV substation. 02 7,5MVA transformers supplying energy for the factory. Work for Siemens Ltda on Av. Mutinga, São Paulo. Supply of civil and electromechanical project, construction work and grounding network.

COCA-COLA SUBSTATION FEMSA group in Jundiai/SP: new 138kV substation. 02 22MVA transformers supplying energy for the factory. Work for Areva T&D Service group. Supply of civil and electromechanical project, construction work, grounding network e electromechanical assembly.

COCA-COLA SUBSTATION – JV + (M+ Group) in Linhares/ES: New 138kV Substation, 02 5MVA transformers supplying energy for the factory. Work for Areva T&D Service group. Supply of civil and electromechanical project, construction work, grounding network e electromechanical assembly.

VARIANTE 138kV TRANSMISSION LINE in Ilha Solteira/SP: CTEEP Transmission Line for the construction of a new substation arranging the Pioneiros Plant power supply into sections. Work for Pioneiros Bionergia Group from Sud Mennucci SP

CONFECÇÕES J.SERRANO 138kV TRANSMISSION LINE in Vargem Grande Paulista SP. Extension: 4,5km. Round-shaped concrete power pole, coming from Vargem Grande Substation to power distribution company Eletropaulo with the purpose of supplying power to the Confecções J. Serrano Substation. Supply of workforce and project review. Direct contract with J. Serrano Ltda. Construction process Youtube video will be available soon.

SOROCABA SUBSTATION 6 CPFL PAULISTA:
New sectioned 138kV substation with civil and electromechanical project and materials. Partnership contract with Siemens Ltda. AT Sector Jundiaí SP.

SOROCABA SUBSTATION 5 CPFL PAULISTA:
New substation, 02 25MVA 138/15kV transformers. Supply of civil and electromechanical project, earthmoving and lot’s preparation and finishing work. Contract with Siemens Ltda. AT Sector Jundiaí SP.

JUNDIAI SUBSTATION 5 CPFL PAULISTA:
New substation, 02 30MVA transformers + 15kV feeders. Supply of civil and electromechanical project and assembly materials. Contract with Siemens Ltda., SP AT Sector Jundiaí/SP.

CAMPO LIMPO SUBSTATION CPFL PAULISTA:
Guard retrofit, lot’s rebuild and circuits and transformer improvement. Supply of civil project and electromechanical and civil assembly materials. Contract with Siemens Ltda. AT Sector Jundiai/SP

BUTANTÃ BRANCH SUBSTATION in São Paulo – SP: 02 138kV at Butantã Institute connecting with Eletropaulo-AES to the new Butantã Substation with 800m of round-shaped concrete power poles. Supply of assembly and construction work workforce. Assembly contract with LEG Engineering in Cravinhos SP

SERVICE PACKAGE

05 SUBSTATIONS NORTHWEST REGION CPFL PAULISTA with circuit breaker J3p138kV exchange, Sec3p138kV Setup, TPs TCs: Getulina Substation, Guararapes Substation, José Bonifácio Substation, Nova Grana Substation and Presidente Alves Substation. Supply of civil and electromechanical project and materials. Direct contract with CPFL Paulista/CPFL Energia SA.

AMPARO SUBSTATION CPFL PAULISTA: Guard retrofit and circuit breaker J3p138kV exchange with supply of civil, electromechanical and electrical project and civil and electromechanical assembly materials. Contract with CPFL Paulista/Energia SA.

STO ANTÔNIO DO ARAGANGUÁ-SP SUBSTATION 34,5kV of CPFL PAULISTA: Contract with Siemens Ltda AT Sector Jundiai SP, with supply of civil and electromechanical project, earthmoving and electromechanical materials.

CASA BRANCA SUBSTATION CPFL PAULISTA: 20MVA 138kV assembly transformer and 03 15kV output feeders. Supply of civil and electromechanical project. Contract with Siemens Ltda.

ITAPETININGA SUBSTATION 9 CPFL PAULISTA: 20MVA 138kV transformer assembly and 03 15kV output feeders. Supply of civil and electromechanical project. Contract with Siemens Ltda. AT Sector Jundiai SP.

GAMERINDOS SUBSTATION RIO DE JANEIRO/RJ: Retrofit services and GIS138kV substation maintenance of Light power distribution company in Rio de Janeiro. Supply of workforce and supervision to Alstom Grid-SP.

SADIA SUBSTATION IN UBERLANDIA/MG:
New 138kV substation with 02 20MVA 138/15kV transformers. Supply of civil and electromechanical project, construction work and electromechanical assembly. Contract with Alstom Grid-SP.

SANTANDER BANK SUBSTATION in Barão Geraldo/Campinas-SP: Sectioned 138kV substation and 04 20MVA transformers supplying Santander’s Data Center. Supply of civil and electromechanical project and assembly materials. Contract with Siemens Ltda. and CPFL Paulista.

SERVICE PACKAGE
05 138kV SUBSTATIONS CPFL PAULISTA: Supply of civil, electrical and electromechanical project. Supply of relay retrofit equipment, exchange of circuit breakers and keys, TPs and TCs to substations: Getulina, Guararapes, José Bonifácio, Nova Grana e Presidente Alves. Direct contract with CPFL Energia through SAP-Emais system.

MORRO DO CIPÓ SUBSTATION: CPFL PAULISTA’s 138kV; GVO Circuit breaker exchange. Supply of civil, electrical and electromechanical project and assembly. Contract with Siemens Ltda. AT Sector Jundiai SP

AGC SUBSTATION (‘Glass Europe’ Belgian) in Guaratinguetá SP: New substation with 02 30MVA 138/13,8kV transformers in isolated cables. Supply of civil and electromechanical project, construction work and electromechanical assembly. Partnership contract with Siemens AT Sector, Jundiai SP.

SERVICE PACKAGE

10 SUBSTATIONS CPFL PAULISTA: New substations, setup of second power transformer, expansion of the 15kV electric lathes and 138kV bays, feeders setup and retrofit relays. Contract with Siemens Ltda.:

*Campinas Substation 19, Ciatec neighborhood: New substation, 01 20MVA Transformer+ 15kV feeder bay.
* Araraquara2 (Uirapuru): Second 20MVA transformer setup.
* RibPreto12(South): Second 20MVA Transformer setup + 15kV feeder bay.
*S.Carlos3(Paraiso): Second 20MVA Transformer setup + 15kV feeder bay.
*RibPreto7(LeãoXIII): Power transformer exchange.
*SCarlos1: 15kV Recloser setup
*S.Carlos4(Bethania):15kV Recloser setup
*Pinhal1: 15kV Recloser setup
*Campinas17(MonteD’Este): Second 20MVA Transformer setup.
*Rib.Preto Iguapé: 13,8kV Capacitors Bank setup.

SERVICE PACKAGE
04 SUBSTATIONS CPFL PAULISTA: Safety relay retrofits, exchange of power transformers and regulators in the following substations: Batatais, Ibitinga, Colina and Taquaral-Campinas. Direct contract with CPFL energia through SAP system.

05 SUBSTATIONS CPFL PAULISTA: CASA BRANCA SUBSTATION, Itapetininga substation II, Jundiai5, Sorocaba5 (São Bento) and Sorocaba6 (southeast): Supply of civil and electromechanical project and grounding network. Contract with Siemens Ltda. AT Sector Jundiai SP

POSTO 6 SUBSTATION – LIGHT RIO DE JANEIRO/RJ: GIS138kV maintenance services. Contract with Alstom Grid, supplying maintenance and cleaning materials, as well as specialized workforce.

ITAU DATA CENTER SUBSTATION in Mogi Mirim: CTEEP power distribution company, new sectioning substation with 06 30MVA 138/13,8kV transformers. Supply of civil and electromechanical project, construction work and assembly. Contract with Siemens Ltda. AT Sector Jundiai/SP.

SIDERURGICA GV SUBSTATION IN PINDAMONHANGABA SP: New substation coming from 2 CTEEP’s transmission lines, with 120MVA and 50MVA 230kV/13,8kV transformer. Output in isolated cable to EFACEB do Brasil Ltda. Supply of civil, electrical and electromechanical project, construction work and assembly. Construction work in progress.

MINERAÇÃO SAMARCO in Mariana MG: 5,2MVA 13,8kV Capacitor Banks setup at Samarco II substation – CEMIG power distribution company. Supply of workforce and electromechanical project to the assembly’s finalization. Contract with Siemens Ltda. AT Sector Jundiai SP.

SAPEAÇU-TAESA SUBSTATION in Sapeaçu/BA: ‘SCV’ Statics compensation system setup, with 04 1p83MVA x 230kV-19,9kV transformer in SCH80 Ø6 aluminum tubes. Supply of civil project, construction work and electromechanical assembly. Contract with Siemens Ltda. AT Sector AT Jundiai SP.

CERQUILHO III SUBSTATION SP COPEL: New substation. 03 150 MVA 230kV/138-13,8lV Autotransformers . Supply of civil and electromechanical project, construction work and electromechanical assembly. Contract with Siemens Ltda. AT Sector Jundiai SP.

TIETÊ PLAZA SHOPPING São Paulo Capital: New substation with 02 7,50MVA 138/13,8kV transformers, stem from Eletropaulo-AES transmission line. Substation’s civil and electromechanical project and project and execution of 800m stem strand. Contract to Siemens Ltda. AT Sector Jundiai SP.

BASF FACTORY in São Bernardo do Campo SP: Expansion of the substation, 02 15MVA 138/13,8kV transformers, output in isolated cables, safety retrofit and measurements. Power distribution company CTEEP. Contract with Siemens Ltda. AT Sector Jundiai SP. Supply of civil and electromechanical project, construction work and assembly.

SUZANO PAPEL & CELULOSE in Imperatriz MA: Supply of electrical-specialized workforce with the purpose of finishing the 230kV Substation assembly, control and power cables and 230kV lathes. Supply contract with Siemens Ltda. Industrial Sector Av. Mutinga Pirituba S

AGUA VERMELHA SUBSTATION – AES-ELETROPAULO in Iturama MG: Contract with VOITH HYDRO São Paulo. Sec3p440kV maintenance and 03TP1p440kV and 06TC1p440kV commissioning.

HONDA MOTORS DO BRASIL: New 138kV substation in Itirapina SP, construction of new 138kV substation, supplying all equipment, control systems, measurements and protection, construction work and assembly with 02 138kV auto transfer Bay, standard 2×25/32MVA, 13,8kV output in isolated cable. Contract with ELEKTRO-IBERDROLA Engineering – Campinas SP.

SERVICE PACKAGE: 05 SUBSTATIONS – CPFL Paulista and Piratininga contract with CPFL Energia Campinas, package Nº18-2140 SC0151 construction and substations’ retrofit, with the supply of panels, control, construction and electromechanical assembly.
New Jundiai Substation 7 – Standard
2x40MVA 138kV with 06 outputs
15kV feeders

New Itatiba Substation
4 Santa Rosa Standard 2×16,6MVA 138kV with 05 15kV feeders.

New São Vicente Substation
3 Rio Branco Standard 2x40MVA 138kV with 15 15kV feeders and C1&C2 circuits sectioning from Praia Grande Transmission Line.

São José do Rio Preto SUBSTATION 5 Austa
Second 30/40MVA 138kV transformer with 07 outputs of 15kV feeders and control system and safety retrofit with expansion of the Control House.

Itu Rondon SUBSTATION: rearrangement to the standart 2x40MVA 138kV with 05 outputs of the 15kV feeders with sectioning of 2 88kV circuits CTEEP West-Salto and connection of the new Substation in TAP, deriving utilizing and existent DB tower.

PIRACICABA 9 UNINORTE SUBSTATION – CPFL Paulista: Contract with CPFL Energia Campinas, SC0413, 138kV bays refurbishment, retrofit, transmission lines protection panel, circuit breaker 138kV exchange and C2 Circuit Sectioning of the Piracicaba-Santa Barbara Transmission Line.

RIO GRANDE 1 SUBSTATION in Rio Grande-RS, contract with CEEE, construction of 13,8kV complete module, with the supply of equipment, civil work and electromechanical assembly.
SIEMENS CONSORTIUM – Execution of the Cequilho III 230kV substation and sectioning of the 230kV Edgar Souza transmission line in Botucatu, with electrical and electromechanical assembly of the equipment required to its implementation. Being the main equipment installed: 03 150MVA transformers, 02 138kV Capacitors Bank, 50MVar, three polar switch disconnectors, circuit breakers, power transformers, auxiliary services panels and power generating set protection and control.

GV DO BRASIL INDUSTRIA E COMERCIA DE AÇO LTDA: Electrical and electromechanical execution and assembly of a 230kV x 120MVA power substation.
Services detailed:
02 230kV gaps to the connection of the TR1 and TR2 autotransformers;
01 230/34,5kV – 120MVA autotransformer;
01 230/13,8kV – 50MVA autotransformer;
02 230kV line entry gap;
02 230kV bars;
01 230kV bar connecting gap;
01 set of 6 13,8kV cubicles to the auxiliary services;
Protection, control, supervision, measurement and billing systems;
Telecommunication and teleprotection systems;
CCTV System;
Power generating set system.
Special protection system.

ARARAQUARA II SUBSTATION: Contract work to the electrical and electromechanical assembly with material and workforce supply for partial fulfillment of the contract n. CT46369 between EFACEC DO BRASIL LTDA and COPEL TRANSMISSÃO S/A; being: Control and protection system, launching and connection of cables, patio lighting, auxiliary services assembly, power generating set assembly, SP DA, assembly of the rigid lathes with sold in aluminum tubes and commissioning.

MATA DE SANTA GENEBRA TRANSMISSÃO S.A – (Work in Progress) – State Power distribution company located on Rua Real Grandeza nº274, ground floor, Botafogo neighboord in the city of Rio de Janeiro. Registered under the nº 19.699.063/0001-06 on the National Registry of Legal Entities (CNPJ), in this statement entitled “The contractor” on one side, and on the other, CONSORCIO ALSTOM GRID/ETE – LOTE A_007/2013

EXPANSION OF SANTA BARBARA D’OESTE 440kV SUBSTATION, Static Var Compensator (-300, +300) Mvar – ALSTOM in Santa Barbara do Oeste – SP, supply, under a fixed-price contract, of equipment, type and operation tests, including execution of services, topography, survey, measurement of soil’s resistivity, executive project as well as construction work services and electromechanical assembly of the 500/400kV (9+1R) x 400 MVA Fernão Dias substation’s construction.

ARTECHE TAIBA WIND FARM– CE (Work in Progress) – Supply, under a contract, of the following services: construction work, electromechanical assembly, electrical installation for 1 4Mvar reactor bank, in the substation of the Taiba Wind Farm, located in São Gonçalo do Amarante – CE (60km from Fortaleza)

ARTECHE RIACHÃO WIND FARM – RN (Work in Progress) – Supply, under a contract, of the following services: construction work, electromechanical assembly, electrical installation for 1 12Mvar reactor bank in the substation of the Riachão Wind Farm, located in Mirim – RN (36km from Natal)

hidreletrica linha-de-transmissao parque-eolico subestacao